CS FundamentalsHardCognizant · Capgemini pattern

A Scrum team's last three sprints delivered 28, 32 and 30 story points. 240 points remain in the backlog and sprints are 2 weeks long. Using average velocity, about how long will the remaining work take?

  1. A. 16 weeks
  2. B. 8 weeks
  3. C. 15 weeks
  4. D. 24 weeks

Correct answer: A. 16 weeks

Average velocity = (28 + 32 + 30)/3 = 30 points per sprint. 240/30 = 8 sprints × 2 weeks = 16 weeks. 8 weeks is the sprint count mistaken for weeks.