Using basic COCOMO for an organic project (E = 2.4 × KLOC^1.05 person-months), what is the estimated effort for a 32 KLOC project?

  1. A. About 77 person-months
  2. B. About 91 person-months
  3. C. About 146 person-months
  4. D. About 14 person-months

Correct answer: B. About 91 person-months

E = 2.4 × 32^1.05 ≈ 2.4 × 38.05 ≈ 91.3 PM. 77 forgets the exponent (2.4 × 32); 146 uses semi-detached constants (3.0 × 32^1.12); 14 is the development time in months (2.5 × E^0.38).