Using basic COCOMO for an organic project (E = 2.4 × KLOC^1.05 person-months), what is the estimated effort for a 32 KLOC project?
- A. About 77 person-months
- B. About 91 person-months
- C. About 146 person-months
- D. About 14 person-months
Correct answer: B. About 91 person-months
E = 2.4 × 32^1.05 ≈ 2.4 × 38.05 ≈ 91.3 PM. 77 forgets the exponent (2.4 × 32); 146 uses semi-detached constants (3.0 × 32^1.12); 14 is the development time in months (2.5 × E^0.38).
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- For the code if (x > 0) { y = 1; } followed by print(y), a single test with x = 5 is run. What coverage does it achieve?
- A server has a mean time between failures of 990 hours and a mean time to repair of 10 hours. What is its availability?
- A new build arrives and testers first run a small, broad set of checks (does it install, launch, log in, open the main screens?) before…
- You are halfway through a change when an urgent bug needs fixing on the same branch. Which command shelves your uncommitted changes so the…
- A Dockerfile ends with CMD ["python", "app.py"]. The container is started with docker run myimage python test.py. What runs?
- Which practice is the defining feature of Kanban rather than Scrum?