Quantitative AptitudeVery hardSSC CGL · RRB NTPC
A certain number of workers can finish a job in 30 days. If there were 10 workers fewer, it would take 10 days more. The number of workers is:
- A. 50
- B. 40
- C. 20
- D. 30
Correct answer: B. 40
Man-days are equal: 30N = 40(N − 10) → 30N = 40N − 400 → N = 40.
हिंदी में
कुछ कर्मचारी किसी कार्य को 30 दिन में पूरा कर सकते हैं। यदि 10 कर्मचारी कम होते, तो उसमें 10 दिन अधिक लगते। कर्मचारियों की संख्या कितनी है?
- A. 50
- B. 40
- C. 20
- D. 30
उत्तर: B. आदमी-दिन समान रहते हैं: 30N = 40(N − 10) → 30N = 40N − 400 → N = 40।
More Time and Work questions
- A contractor undertakes to build a road in 40 days with 50 men. After 20 days he finds that only one-third of the road is built. How many…
- Two inlet pipes fill a tank in 10 and 15 hours and an outlet empties it in 12 hours. All three are opened on an empty tank; after 4 hours…
- How many of the following statements are correct? 1. If A is twice as efficient as B, A takes half the time B takes. 2. If 2 men do as…
- A and B undertake to do a work for ₹1,200. A alone can do it in 6 days and B alone in 8 days. With the help of C they finish it in 3 days…
- A and B together can do a work in 12 days, and B and C together in 16 days. A worked for 5 days, B for 7 days and C finished the remaining…
- A can finish a work in 20 days and B in 30 days. In how many days can they finish it together?