Tasks and durations (days): A 3; B 4 (after A); C 2 (after A); D 5 (after B and C); E 1 (after C). What is the total slack (float) of task C?

  1. A. 0 days
  2. B. 6 days
  3. C. 2 days
  4. D. 1 day

Correct answer: C. 2 days

Paths: A–B–D = 12 (critical), A–C–D = 10, A–C–E = 6. Project length 12. D must start by day 7, so C must finish by 7 (its late finish); C can start at 3 at the earliest and finish by 5. Slack = 7 − 5 = 2. 6 days uses only path A–C–E and ignores that D waits for C.