CS FundamentalsHardIBM · Deloitte pattern
An SLA promises 99.9% availability over a 365-day year. What is the maximum downtime it allows, and how much does moving to 99.99% allow?
- A. About 8.76 hours; about 52.6 minutes
- B. About 8.76 hours; about 5.26 minutes
- C. About 52.6 minutes; about 5.26 minutes
- D. About 87.6 hours; about 8.76 hours
Correct answer: A. About 8.76 hours; about 52.6 minutes
A year has 8760 hours. 0.1% × 8760 = 8.76 h. 0.01% × 8760 h = 0.876 h ≈ 52.6 min. 5.26 minutes is the 99.999% ('five nines') figure.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- How many of the following statements comparing containers and virtual machines are correct? 1. A Linux container can run directly on a…
- A Dockerfile reads: FROM python:3.12 COPY . /app RUN pip install -r /app/requirements.txt Every small code edit makes the build reinstall…
- How many of the following statements about Kubernetes are correct? 1. A Pod is the smallest deployable unit and can never hold more than…
- Match each project situation with the most suitable SDLC model. P. Requirements fixed and well understood, short project Q. Large…
- How many of the following statements about Scrum are correct? 1. A sprint may be extended by a few days when the sprint goal has not yet…
- In top-down integration testing, the top-level module is ready but the lower-level modules it calls are not. What must the testers write…